Thanks to meticulous planning and collaboration between TAFE NSW, JLL and the Precise Air teams, the helicopter lift of 15 air conditioning units at TAFE NSW Wyong was completed in just 20 minutes and 56 seconds from engine start to landing – a fraction of the time of a conventional crane lift.
Safety and efficiency were our top priorities for the installation at Wyong. The day began with the landing of the helicopter at 7:30 AM and introduction of the crew to the team. Our Project Manager, Sergio Tovar, conducted the toolbox talk to ensure everyone understood the safety protocols in place and each individual’s role in the operation. Clearly marked exclusion zones prevented unauthorised access.
This installation at the TAFE NSW Wyong Campus is just the latest milestone in our ongoing program of HVAC and fire upgrades for TAFE NSW. Our Precise Air and Precise Fire teams are delivering these essential upgrades to over 70 sites throughout the state. Our mission is to partner with our clients, TAFE NSW and JLL, to create comfortable and safe learning environments for students, staff and the community.
Please take a look at some of the highlights.
We are proud to support The Safer Air Project - playing a leading role in national IAQ advocacy, public awareness, education and policy influence.
2 March 2026
News
Precise has been recognised by Avetta as a 2025 ESG Innovator, reflecting our commitment to responsible environmental, social, and governance practices.
29 January 2026
News
The Precise Air group of companies’ operations in the West continue to expand with the extension of our Harvey Norman contract across Western Australia.
18 December 2025
News