News
Collaboration, planning and safety systems critical for high rise installations
23 May 2024

This weekend, we installed the latest AIRSTAGE chiller from Fujitsu General Australia at 14 Martin Place for Abacus Group.
The skill shown by the riggers from SP Rigging and the Borger Cranes operator made the whole process look effortless. The operation required a team of riggers to remove the external louvre to the level 9 plant room and carefully manoeuvre the multi-ton unit into a narrow opening between high-rise buildings. Moving it into the plant room was like threading a needle.
Safety was our top priority, so we meticulously planned every step and followed stringent safety precautions for this high-risk operation. Even with Sydney’s unpredictable weather, we were blessed with clear skies during the four-hour window for the crane lift.
Overall, we’re really proud of how everyone came together to complete this complex installation with such precision and teamwork. Great work Navid Hamidi and Jerry Timor.
To find out more, contact Alex Hadigol, General Manager Construction, on 1300 728 250.
Related Articles
A smarter way to connect what matters
Building intelligence only creates value when somebody is accountable for turning it into an outcome
9 November 2026
Bringing industry expertise to the national conversation
Phil Gacitua and Andrew Waugh attended the Safer Shared Air: Indoor Air, Health and Productivity Conference at Parliament House in Canberra, joining experts, health professionals, advocates, researchers, patient organisations, peak bodies and industry representatives for an important national conversation
28 October 2026
News
From Copilot to Colleague – AI Agents in Property
Mark Dunn, Precise's General Manager of Digital Services, joined Yardi’s Bernie Devine CPA Devine and Addaptive’s David Benett on the masterclass, "From Copilot to Colleague – AI Agents in Property" panel at The Property Congress
27 October 2026
News, Case Studies